Sydney Aquarium

Seal Enclosure for Sydney Aquarium

Highly corrosive environment required hot dip galvanization and a 2-part epoxy paint system. Structure installed on an existing floating barge, temporary ramp installed to base of barge in order to gain access for crawler crane. Crane used to install structure, removed on completion.

Features:

  • Value: 215,000 + GST
  • Architect: Misho + Associates
  • Builder: Sydney Aquarium / Carson Group
  • Structural: Steel; Approx. 24,000 KG
  • Fabrication: 6 Weeks
  • Installation: 6 Weeks
1 / 2 Sydney Aquarium
Sydney Aquarium
2 / 2 Sydney Aquarium
Sydney Aquarium

Bambu Restaurant

Sydney Cove International Passenger Terminal

Very tight program, all steel including 18 metre 700 WB beam, delivered into site through standard double access doors using portable roller benches taking only 3 hours using 2 fork lifts.

Features:

  • Value: 86,000 + GST
  • Architect: Misho + Associates
  • Builder: Eric Giadullo
  • Structural: Steel; Approx. 13,500 KG
  • Fabrication: 1 Weeks
  • Installation: 1 Weeks
1 / 3 Bambu Restaurant
Bambu Restaurant
2 / 3 Bambu Restaurant
Bambu Restaurant
3 / 3 Bambu Restaurant
Bambu Restaurant

Waterfront Restaurant

5 suspended curved ceilings

5 suspended curved ceilings. Very quick turn-around to meet construction program needs. Each suspended unit required 4 different radii to form required shape. All units fabricated whole then cut in half. Sections craned through second storey window then site welded together in very confined space. Lifted into position with 2 gennie hoists and fixed to existing rafters.

Features:

  • Location: The Rocks, Sydney
  • Value: 86,000 + GST
  • Architect: Misho + Associates
  • Builder: Eric Giadullo
  • Structural: Steel; Approx. 13,500 KG
  • Fabrication: 1 Weeks
  • Installation: 1 Weeks
1 / 4 Waterfront Restaurant
Waterfront Restaurant
2 / 4 Waterfront Restaurant
Waterfront Restaurant
3 / 4 Waterfront Restaurant
Waterfront Restaurant
4 / 4 Waterfront Restaurant
Waterfront Restaurant

Garden Island, Sydney

Fences, pedestrian gates and 8m double auto-vehicle gates

Heritage listed site. Fence and gates to be sympathetic to existing historical environment. Fence erected to divide the northern tip of the island comprising historical garden and buildings from southern side which comprised defence industry. This made the north accessible to the public, which had never been the case. The fence needed to include a large vehicle auto access gate for high volume usage. The client had high security needs for pedestrian and vehicles, security card access was essential.

Features:

  • Value: 190,000 + GST
  • Architect: Stuart Pty Ltd / Man of Steel
  • Builder: Stuart Pty. Ltd.
  • Structural: Approx. 170 linear metres of heavy steel fencing following site countour
  • Fabrication: 4 Weeks
  • Installation: 4 Weeks
1 / 5 Garden Island
Garden Island
2 / 5 Garden Island
Garden Island
3 / 5 Garden Island
Garden Island
3 / 5 Garden Island
Garden Island
4 / 5 Garden Island
Garden Island

PYD

Project completed in two stages. Stage one: Stiffen and strengthen existing beams, remove columns, add mezzanine to existing first floor. Stage two, stiffen existing beams, remove beams, temporarily prop existing roof and remove one side of this roof, replace with new higher roof including an atrium. Provide new mezzanine to existing first floor, fabricate and install 25mm plate steel blade walls to entry.

This project required a very fast turn around time as the client was still trading during construction. Difficulties included very limited access to first floor of building and limited head height. All mezzanine steel was erected with 1,500 kg walk behind electric forklifts.

Features:

  • Location: Danks St, Waterloo, Sydney
  • Value: 620,000 + GST
  • Architect: Mac Interactive
  • Builder: MPA Projects
  • Structural: Steel; Approx. 70,000 KG
1 / 5 PYD
PYD
2 / 5 PYD
PYD
3 / 5 PYD
PYD
4 / 5 PYD
PYD
5 / 5 PYD
PYD

Schlindlers Lift Test Facility

Modification and relocation

Modify three existing structural steel lift shafts and access walkways. Man of Steel built and installed two of the original shafts. Identify and stamp all steel members, dismantle structure and transport to painters and erect at new site. Tight time frame; 3 weeks to modify and disassemble, 1 week to paint, 1 week to install. These test shafts are used to train technicians and to show potential customers Schlindlers products. This structure is the centre-piece of their Australasian headquarters.

Features:

  • Location: Mascot, Sydney
  • Value: 90,000 + GST
  • Designers: Schlindlers
  • Builder: Schlindlers / Man of Steel
  • Structural: Steel; Approx. 20,000 KG
1 / 5 Schlindlers Lift Test Facility
schindlers lift test facility
2 / 5 Schlindlers Lift Test Facility
schindlers lift test facility
3 / 5 Schlindlers Lift Test Facility
schindlers lift test facility
4 / 5 Schlindlers Lift Test Facility
schindlers lift test facility
5 / 5 Schlindlers Lift Test Facility
schindlers lift test facility

Action Sports Facility

Modification and relocation

Fast simple structure, slab being pre-cast concrete suspended between parallel 180 PFC channels. Channels laid first hen a series of portal frames bolted to PFC channels, purlins and girts bolted to portals.

Features:

  • Location: Olympic Park, Homebush Bay
  • Value: 95,000 + GST
  • Architect: Lahz Nimmo
  • Builder: Les Moore Projects
  • Structural: Steel; Approx. 12,000 KG
  • Fabrication: 2 Weeks
  • Installation: 1 Weeks
1 / 1 Action Sports Facility
action facility

Pyrmont Aparments

Pyrmont Apartments, Pyrmont

Fabricate full height structural steel balcony enclosures, hot dip galvanize crane into position then fix. Benefits: No on-site welding, fast installation time, balustrades and handrails (approx. 85 linear metres) also supplied by Man of Steel.

Features:

  • Location: Pyrmont, Sydney
  • Value: 70,000 + GST
  • Architect: Corben Architects
  • Builder: Pyrmont Engineering
  • Structural: Steel; Approx. 10,000 KG
  • Fabrication: 2 Weeks
  • Installation: 3 Weeks
1 / 3 Pyrmont Aparments
pyrmont apartments
2 / 3 Pyrmont Aparments
pyrmont apartments
3 / 3 Pyrmont Aparments
pyrmont apartments
Structural Steel, contemporary architectural metalwork. Quality design, construction & installation.